Folger Drive Emergency Operations Center Project

Project Status Update: On Hold (Spring 2026)

Following a careful review of the increasing costs associated with all the District’s capital projects under development, project benefits and risks, and available funding, the MPWD Board of Directors made the difficult decision to put the Folger Drive Emergency Operations Center (EOC) Project on hold. This decision was necessary for the District to prioritize other critical, near-term water infrastructure needs across our service area.

Construction proposals for the Folger project were received in February 2026, and the actual construction costs were substantially higher than when the project was originally scoped.  At the same time, due to a number of factors, costs associated with several of the District’s other capital improvement projects were also increasing.  Therefore, the Board of Directors requested that staff review all capital improvement project budgets and perform financial modeling of several different cost scenarios and the impacts on the Capital Improvement Program (CIP) as a whole, and recommend priorities based on current information.  Following this review, the Board determined that it is in the best financial and practical interests of our ratepayers to put the Folger Drive EOC project on hold for the time being. The property at 1510 Folger Drive will remain in its current state and continue to be utilized for District storage for the time being, with some minimal electrical upgrades.

Project Background: The Mid-Peninsula Water District (MPWD) has owned the 1510 Folger Drive property for more than 80 years. The site has a 3,290 square foot office building with parking lot, which is currently being used for storage. The MPWD plans to renovate the site to serve as its Emergency Operations Center (EOC). The project will allow the MPWD to maintain our community’s critical drinking water infrastructure and secure firefighting water supply during and after emergency events. While the long-term goal of establishing a dedicated EOC remains, the District has identified alternative near-term solutions to maintain operational continuity.

image showing location of the Folger Drive facility

Project Scope: (Proposed/On Hold) Modernization of the site will include seismically retrofitting and improving the existing building’s electrical, telecommunications, and plumbing infrastructure as well as fire and life safety features. It will also include the addition of a 1,300 square foot pre-fabricated storage facility and landscaping improvements. These upgrades will provide the District with an EOC that will support continued operations following emergencies large and small, including major regional events such as flooding, fire, and earthquakes.

Project Schedule: This project is currently on hold indefinitely. No construction is planned to occur at this time. The District will continue to monitor the needs of the community and will update this page if the Board decides to reactivate the project in a future Capital Improvement Program (CIP) cycle.

architectural and landscape renderings of the proposed modifications to the MPWD Folger Drive facility.

FAQs

Q. What does Mid-Peninsula Water District (MPWD) do?
MPWD provides drinking water and fire service water to more than 30,000 residents and 500 business, and with eleven emergency interties to neighboring water systems, is an integral part of the peninsula’s connected water systems. The District was established in 1929 and has been serving the community for more than 95 years. The District’s service area includes the City of Belmont and portions of the Cities of San Carlos, Redwood City, and Unincorporated San Mateo County.

Q. Why is MPWD repurposing 1510 Folger Drive as an Emergency Operations Center (EOC)?
The District’s operations center at 3 Dairy Lane in Belmont flooded during a New Year’s Eve storm at the end of 2022. This event highlighted the vulnerability of our Dairy Lane facility to flooding and, given its location, the potential for significant access issues during other disaster events.

The District is responsible for maintaining 95 miles of water mains and other critical water infrastructure in the service area that provide drinking water and support firefighting throughout the community. The Folger Drive EOC will enhance the District’s ability to respond to emergencies within our system in all situations.

The Folger Drive property is in an ideal location to serve as an EOC because it is not in an identified hazard area (flood, liquefaction risk, or high fire risk). The lot can accommodate a modest, new storage facility that would allow for storage of equipment critical for repairing the water system during an emergency. Furthermore, because the District owns this property, it will not incur the significant expense of acquiring a new property for an EOC.

Project site plan for the Folger Emergency Operations Center.

Q. When is construction expected to occur and how long will it last?
Construction is currently on hold. While the physical improvements are designed to take approximately 10 months, the District has postponed contract awards to prioritize other urgent water main and storage tank replacement projects. No neighborhood traffic or parking impacts are anticipated since no work is scheduled.

Q. What is the history of the Folger Drive property owned by MPWD?
The District has occupied the Folger Drive Property for more than 80 years. This was one of two properties previously used for District operations until the District acquired its Dairy Lane facility in the early 2000s. The 27,000 square-foot lot houses a two-story office building that has been in use since the 1980s, as well as a parking lot. Prior to the construction of the existing office building, the site was used for a District water storage tank, pump station, and storage facility.

Q. What impact will the future Emergency Operations Center have on its neighbors?
After the EOC project is complete, the MPWD does not expect a significant change in current site use intensity, except in the case of emergencies that could impact water supply and distribution. Since the site already has adequate parking, there will be no undue parking burden on the neighborhood. A sidewalk will be added in front of the building.

Q. I live nearby. How will construction impact my view and the availability of parking?
The existing fence around the property at 1510 Folger Drive will stay in place, and it will shield most construction activity from view. This property already contains adequate parking and can accommodate construction workers’ vehicles and future MWPD employee use without impacting neighborhood street parking.

street views of the Folger Drive facility showing the sight lines from the street for neighbors.

Q. What other options did MPWD consider for its Emergency Operations Center?
MPWD’s Operations Center at 3 Dairy Lane in Belmont was flooded during the New Years Eve 2022/2023 flooding event. As the District worked to recover from this disaster amid climate change, the staff and the Board assessed other potential future risks to the District and developed a plan to not only recover the damage, but to take this opportunity to move forward by mitigating the suite of risks we could face over the next 75 or more years. We looked at all property owned by the District as well as the potential to buy new property. Modernizing the District’s existing Folger Drive property was determined to be the most cost-effective and efficient way to provide the District with the ability to provide continual service to the community through emergencies. Its location is well-suited as an EOC because it is outside of any identified hazard area (flood, liquefaction risk, and high fire risk), does not require the purchase of a new property, and has an existing office building that can be readily modernized.

In Spring 2026, the Board determined that it was necessary to defer the formal Folger EOC construction. If an emergency occurs during construction at our Dairy Lane facility, operations can temporarily utilize the Folger site as-is, using the existing garage bays for shop space without undergoing the multimillion-dollar office remodel. This keeps our workforce resilient while conserving funds for more critical system-wide infrastructure.

Q. What will the new storage building be used for?
The new storage building will be used to store tools, equipment, and pipe parts needed to respond to emergency water main breaks and other typical emergency system maintenance. The building will include work space to support system repairs. A pre-fabricated metal building was selected due to its lower cost and because it reduces overall construction time onsite. The exterior of the new building will be styled to be consistent with the residential surroundings.

Q. How does the MPWD prioritize its capital improvement projects?
The MPWD Capital Improvement Program (CIP) is the backbone of the District’s efforts to ensure a reliable and sustainable water supply for the future. The CIP is a comprehensive plan that outlines the projects necessary to maintain and upgrade our water infrastructure to enhance the quality of our services, increase system reliability, and meet the growing demands of our community. MPWD completed an update of its CIP in 2024, which is available HERE. MPWD anticipates completing its next CIP update in Summer/Fall of 2026.

This proposed project to create an EOC is included in our 5-year CIP budget and is integral to making sure that the District can continue to serve the community with excellent reliability and customer service for years to come.