Capital Improvement Project Update - September 2022

Hastings Drive / Vine Street / Belmont Canyon Road Water Main Improvements

As of August 31, 2022, C2R completed all project work including final trench paving, slurry seal, and striping. The District deemed the project substantially complete on August 30, 2022 and issued the project punchlist with a desired completion date by September 16, 2022.

Change Order No. 3 for $7,290.45, includes 5 separate daily extra work report (DEWR) inclusive of several City requested items (additional traffic control plans, work stoppage/delay associated with the concrete valley gutter, and special driveway finishing for the resident at 3204 Upper Lock Ave), Spring Ln service reconnections, and additional striping. This change order also adds 3.5 working days increasing the contract days from 98 to 101.5. Please refer to Change Order No. 3 for additional information.

Balancing Change Order No. 1 increases the original contract total by $6,915.75 to account for additional materials used during the project. This adjusts the original bid quantities to reflect the actual constructed quantities.

Image of constructions workers finishing up the Hastings project in August 2022

Image of constructions workers finishing up the Hastings project in August 2022

Image of constructions workers finishing up the Hastings project in August 2022