Capital Improvement Project Update - June 2022

Hastings Drive / Vine Street / Belmont Canyon Road Water Main Improvements

As of May 27, 2022, C2R completed all main line installation along Vine Street (1,445 LF 8" DIP) in addition to all 14 service connections, 3 hydrants, and other miscellaneous appurtenance including cathodic protection items. C2R successfully conducted the 2‐hour pressure test on May 20, 2022 and proceeded to disinfect/flush the water main before beginning the tie‐in connections. On May 27, 2022, C2R made the first of three tie‐in connections along Vine Street beginning at Courtland Road.

June 2022 work includes the remaining tie‐in connections along Vine Street at Arden and Spring Lanes, installation of the Spring Lane blowoff, and then proceeding to main line installation along Belmont Canyon Road and Upper Lock Avenue.

During pipe installation along Vine Street, C2R encountered sporadic veins of rock/large boulders and an 8" concrete cap within a good portion of the marked alignment. This required specialized equipment to break through the harder material thereby affecting their production rate. The District is currently negotiating with C2R on their Change Order request.

As of May 27, 2022, C2R completed 49% of the contractual work, and has 65 of 95 working days remaining.